Process Skid | Modular Process Unit | Open-Frame / Containerized | Equipment Integration: Pumps / Vessels / Compressors / Heat Exchangers / Instrumentation

Place of Origin: China
Brand Name: YUHONG
Certification: ASME VIII-1 / GB/T 25198 / PED / CE
Model Number: SKID
Minimum Order Quantity: 1 set
Price: Negotiable
Packaging Details: Sea Worthy Package
Delivery Time: 30-100 DAYS
Payment Terms: L/C,T/T
Supply Ability: according to the client's request
Inquiry Now
Get A Quote
Specifications
Highlight Features

Modular Process Skid Unit

,

Open Frame Containerized Skid

,

Pumps Vessels Compressors Skid

Product Description
Overview – Skid as Integrated Process Module

A process skid (skid-mounted equipment or modular unit) is an integrated assembly of process equipment, piping, valves, instrumentation, and control systems mounted on a common structural steel base frame or within a containerized enclosure . The skid is designed as a functionally complete, self-contained unit that is fully prefabricated, assembled, and tested at the manufacturer's facility prior to shipment .

Skid-mounted construction enables modularization of industrial processes, reducing field installation work to positioning the skid, securing it to foundations, and connecting utility and process interfaces . This product is designed and manufactured per ASME Section VIII Division 1, GB/T 25198, PED 97/23/EC, or CE/CPR requirements, with material selection and welding per applicable pressure equipment directives .


Skid Classification – Structural Types
Open-Frame Skid
  • Construction: Structural steel channel or I-beam base frame (open structure)
  • Equipment: Mounted directly on the frame; piping and instrumentation exposed
  • Application: Indoor installations, moderate environments, where visual inspection and maintenance access are required
  • Advantages: Lower weight, easier access for maintenance, lower cost
  • Limitations: Less protection from weather and corrosive atmospheres; requires additional shelter in outdoor service
Containerized Skid (Enclosed)
  • Construction: Equipment housed within a shipping container or custom enclosure
  • Equipment: Fully enclosed with access doors and ventilation
  • Application: Outdoor installations, harsh environments (offshore, desert, arctic), rapid deployment
  • Advantages: Weather protection, temperature control, vandalism prevention, transport-ready
  • Limitations: Higher cost, limited access for maintenance, increased weight

Skid Classification – Functional Types
Type Primary Function Typical Components Application
Pump skid Fluid transfer / boosting Pumps (centrifugal, positive displacement), suction diffusers, discharge headers, VFDs, check valves  Water injection, chemical dosing, oil transfer
Compressor skid Gas compression Compressors, suction scrubbers, aftercoolers, pulsation dampeners  Gas boosting, vapor recovery, LNG
Chemical injection skid Additive dosing Storage tanks, metering pumps, flow meters, check valves, control panel  Corrosion inhibition, scale prevention, hydration suppression
Heat exchanger skid Heat transfer Shell & tube or plate heat exchangers, piping, temperature control valves  Process heating/cooling, waste heat recovery
Separation skid Phase separation Separator vessels, level controls, dump valves, mist eliminators Oil-water-gas separation, condensate knockout
Metering skid Flow measurement Coriolis/ultrasonic meters, flow straighteners, pressure/temperature sensors Custody transfer, process monitoring
Gas conditioning skid Gas treatment Filters, coalescers, heaters, pressure regulators Dew point control, solids removal

Structural Design – Base Frame Parameters

Base Frame Material

  • Carbon steel: A572 Gr.50 or equivalent – standard structural frame
  • Stainless steel: 304L / 316L – for corrosive environments or food-grade service
  • Aluminum: 5-series or 6-series – for weight reduction (e.g., mobile refueling skids) 

Frame Dimensions (Typical)

Parameter Range Notes
Length 2.0m – 12.0m Limited by transport and lifting capacity
Width 1.5m – 4.5m Road transport limit: 4.5m (standard)
Height (equipment) 2.0m – 6.0m Transport height limit: 4.0m (highway) / 6.0m (special)
Frame beam height 150mm – 400mm Selected per equipment load and span
Lifting lug rating 2× skid weight (minimum) Per ASME / design safety factor
Fork pocket dimensions Standard or custom For forklift handling during installation

Equipment Layout – Design Principles

Per modularization design practice, skid layout follows these principles :

  • Vertical arrangement: Tall equipment placed at skid center; shorter equipment and valves located at perimeter for maintenance access 
  • Weight distribution: Heavy equipment positioned over structural supports; center of gravity within 1/3 of skid footprint
  • Maintenance access: Minimum walkway width ≥ 900mm; overhead clearance ≥ 2,150mm 
  • Piping routing: Process piping minimized for compactness; flanged connections at skid boundaries for field tie-in 
  • Instrumentation access: Transmitters and control valves accessible from walkways or platforms 

Piping System – Materials and Fittings

Pipe Materials

Service Temperature Material Specification
-20°C to +425°C Carbon steel 20# / SA-106 Gr.B GB 8163 / ASTM A106
-196°C to +600°C Stainless 304L / 316L ASTM A312 / GB/T 14976
-40°C to +280°C Duplex 2205 ASTM A789
Elevated temperature (> 425°C) Alloy (1.25Cr-0.5Mo / 2.25Cr-1Mo) ASTM A335

Pipe Fittings and Flanges

  • Fittings: Seamless per GB/T 12459 or ASME B16.9
  • Flanges: Weld neck or slip-on per ASME B16.5 / HG/T 20615 (Class 150 – 2500)
  • Flange sealing face: Raised face (RF) – standard; RTJ for high pressure or hydrogen service
  • Gaskets: Spiral wound (SS + graphite) with inner/outer rings; PTFE for instrumentation 
  • Bolting: Stud bolts per HG/T 20634; material 35CrMo with 30CrMo nuts, zinc-plated 

Welding and Inspection

  • Pipe welding: GTAW (root pass) + SMAW or SAW (fill) – per ASME Section IX
  • Weld examination:
    • All butt welds: 100% RT (X-ray) per JB/T 4730 / ASME V – Grade II acceptance 
    • Fillet welds: 100% MT or PT – Grade I acceptance 
  • Post-weld treatment: Pickling and passivation for stainless steel; PWHT per UCS-56 for carbon steel > 38mm thickness 

Skid Integration – Typical Equipment Roster

A process skid may integrate the following equipment (selection based on process function) :

Rotating Equipment
  • Pumps: Centrifugal (ANSI / API 610) or positive displacement (gear, diaphragm, peristaltic)
  • Compressors: Reciprocating, screw, or centrifugal (API 618 / 619)
  • Drivers: Electric motors (TEFC, explosion-proof per NEC / ATEX), diesel engines, or pneumatic
  • Variable frequency drives (VFDs) for speed control 
Static Equipment
  • Pressure vessels: Separators, filters, coalescers, surge drums (per ASME VIII-1)
  • Heat exchangers: Shell & tube, plate-and-frame, or finned tube (per TEMA)
  • Storage tanks: Atmospheric or pressurized (vertical/horizontal)
  • Piping manifolds: Suction and discharge headers with block and check valves 
Instrumentation and Control
  • Flow meters: Coriolis, ultrasonic, magnetic, or turbine
  • Pressure transmitters (PT) and temperature transmitters (TT) 
  • Level transmitters (LT) and level switches (LS) on vessels
  • Control valves (CV) with pneumatic or electric actuators
  • Safety instruments: Pressure relief valves (PRV), emergency shutdown (ESD) 
  • Programmable logic controller (PLC) or distributed control system (DCS) interface
  • Control panel: Explosion-proof enclosure (NEMA 4X / IP65) 
Piping and Valves
  • Isolation valves: Ball valves (full port) and gate valves 
  • Check valves: Swing or spring-loaded – prevent backflow
  • Instrument isolation: Needle valves (316SS) for pressure/temperature tap connections 
  • Drain and vent: Ball valve + needle valve combinations for safe venting 

Fabrication Process – Skid Assembly Sequence
  1. Structural frame fabrication: Base frame welded from structural steel; drilling for equipment mounting and lifting lugs
  2. Equipment placement: Major equipment (vessels, pumps, compressors) positioned and bolted/welded to frame
  3. Piping installation: Process and utility piping installed per isometric drawings; flanged connections at skid perimeter
  4. Instrumentation installation: Transmitters, control valves, and sensors mounted; tubing and wiring routed
  5. Electrical installation: Motors, VFDs, control panels, and junction boxes wired; cabling in conduits or cable trays 
  6. Insulation and cladding: Thermal insulation applied to hot/cold piping; aluminum cladding or jacketing
  7. Surface treatment: Sandblasting (Sa2.5 grade) per GB/T 8923; primer (zinc-rich epoxy), intermediate, and polyurethane finish coat; minimum dry film thickness ≥ 250μm for carbon steel structures 
  8. Testing and pre-commissioning: Hydrostatic testing, pneumatic leak testing, instrumentation loop checks, and functional testing 

Shop Testing – Factory Acceptance Test (FAT)

Per skid manufacturing practice, FAT is conducted at the fabricator's facility prior to shipment :

Test Type Procedure Acceptance Criteria
Hydrostatic test (piping and vessels) 1.3 × design pressure per ASME UG-99; hold ≥ 30 minutes Zero pressure drop; no visible leakage
Pneumatic leak test 0.6 MPa air or nitrogen; soap bubble application No bubbles at joints; leakage ≤ 1×10⁻⁵ Pa·m³/s
Instrument loop test Simulated 4-20mA signals; verify PLC/DCS readout ±0.5% of span accuracy
Functional test Operate pumps/compressors at minimum and normal speed Mechanical integrity; vibration within limits
Electrical continuity test Megger test for insulation resistance ≥ 1 MΩ at 500V
Painting inspection Dry film thickness gauge – 5 random points ≥ 250μm (CS structure); ≥ 100μm (galvanized structure) 

Transport and Lifting Considerations

Skid dimensions and weight are constrained by transport and lifting equipment capabilities :

  • Road transport: Width ≤ 4.5m; Height ≤ 4.0m (standard); Length ≤ 12.0m (standard)
  • Shipping container: 20ft (6.1m) or 40ft (12.2m) for containerized skids
  • Lifting: Skid mass ≤ 30,000kg for single-crane lift; heavier units split into modules
  • Lifting lugs: Designed per ASME BTH-1; rated at 2× skid weight
  • Transport fixings: Clamp or bolt skid to transport frame; protect instruments with covers

Field Installation Requirements

Upon arrival at site, the following installation steps are required :

  1. Foundation preparation: Reinforced concrete foundation with anchor bolts; flatness ≤ 1mm/m
  2. Skid positioning: Crane lifting onto foundation; align with anchor bolt template
  3. Leveling: Shim plates to achieve levelness ≤ 1mm/m (longitudinal) and ≤ 1.5mm/m (transverse)
  4. Securing: Tighten foundation bolts to specified torque
  5. Field connections: Flanged piping tie-in to interconnecting lines (field welding for non-flanged)
  6. Electrical tie-in: Connect power supply and DCS/PLC communication cables
  7. Final commissioning: Site acceptance test (SAT) – repeat FAT at site with process fluids

Application Profiles – Representative Skid Types
Gas Conditioning Skid (Upstream / Midstream)
  • Service: Remove liquids and particulates from natural gas prior to compression or metering
  • Components: Filter coalescer (gas/liquid separation), heater (dew point control), pressure regulator, instrumentation 
  • Design conditions: Operating pressure 0.6 – 3.5 MPa; operating temperature -19°C to +60°C
  • Piping material: Carbon steel 20#; SS 304 for instrumentation tubing 
  • Special features: Electric heat tracing on pressure regulator to prevent freeze-up 
Chemical Injection Skid (Offshore / Onshore)
  • Service: Metered injection of corrosion inhibitors, anti-scalants, or hydrate inhibitors
  • Components: Six 1,000-gallon storage tanks (316SS, sloped bottom); six metering pumps (Waukesha or equivalent); flow meters, check valves; pneumatic control system 
  • Dimensions: 7,400 × 1,250 × 3,500 mm; weight ~10,000 kg (empty) 
  • Frame material: A572 GR50 square tube with drip pan for spill containment 
  • Paint system: Sandblasting, zinc primer, polyurethane finish 
Pump Skid (HVAC / Process Cooling)
  • Service: Chilled water circulation or cooling water distribution
  • Components: End-suction pumps (2 to 5 units; 10–200 kW), suction diffusers, triple-duty valves, common discharge/suction headers, pump controller 
  • Operating range: System head 3–6 bar; flow up to 380 lps 
  • Header size: 150–450mm; skid length 2.1–4.9m (depending on pump count) 
  • Optional components: VFDs, plate heat exchangers, expansion tanks, chemical pot feeders 
CO₂ Recovery Skid (Process)
  • Service: Recover CO₂ tail gas; reduce footprint and construction cost
  • Integration: Vertical oil separators, water-cooled shell & tube exchangers (layered arrangement)
  • Piping material: S30408 (low-temperature), carbon steel 20# (ambient/hot service) 
  • Performance comparison vs. conventional construction:
    • Total investment reduced 72.0% (from ¥3,500万 to ¥980万) 
    • Civil cost reduced 74.0% 
    • Construction area reduced 75.2% (from 1,700m² to 422m²) 
    • Construction period reduced 50.0% (from 6 months to 3 months) 
    • Production capacity and product quality unchanged 

Documentation per Shipment
  • Material test certificates (EN 10204 3.1 or 3.2) – structural steel, piping, vessels, fittings, flanges, instruments
  • Pressure vessel design report and ASME U-stamp data report (if applicable)
  • Piping isometric drawings and weld maps
  • P&ID (piping and instrumentation diagram) – as-built
  • Electrical schematic diagrams and cable routing
  • Hydrostatic test report (with pressure and time records)
  • Pneumatic leak test report
  • NDE reports (RT, PT, MT, UT) – per JB/T 4730 or ASME V
  • Instrument calibration certificates (with traceability) 
  • Safety valve set pressure certificate and calibration report 
  • Painting inspection report (dry film thickness, adhesion test)
  • Factory acceptance test (FAT) procedure and results
  • Operation and maintenance manual (including lubrication schedule, start-up/shutdown procedure)
  • Packing list and shipping dimensions
  • Lifting procedure and center of gravity report

Selection Checklist – Process Skid
  1. Process function – Pumping / Compression / Injection / Separation / Metering / Conditioning / Heat transfer
  2. Process fluid – name, composition, density, viscosity, corrosivity, impurities
  3. Flow rate or capacity – design operating range (minimum, normal, maximum)
  4. Operating pressure – inlet and outlet
  5. Operating temperature – inlet and outlet
  6. Design pressure and temperature – per ASME/GB code
  7. Material selection – Carbon steel / 304L / 316L / Duplex / Alloy (based on fluid corrosivity and temperature)
  8. Equipment type – Pump (centrifugal / positive displacement) / Compressor (recip / screw / centrifugal) / Vessel (vertical / horizontal)
  9. Control requirements – Manual / Local PLC / DCS interface (protocol: Modbus / Profibus / HART)
  10. Electrical classification – Explosion-proof (NEC Class 1 Div 1/2 or ATEX Zone 1/2) / Non-hazardous
  11. Environmental conditions – Indoor / Outdoor / Offshore / Desert / Arctic (affects enclosure and heating/cooling)
  12. Transport constraints – Maximum dimensions and weight for road/ship transport
  13. Codes and standards – ASME VIII-1 / GB/T 25198 / PED / CE/CPR / GOST / DOSH 
  14. Skid type – Open-frame / Containerized
  15. Special features – Heat tracing, insulation, chemical injection, sampling ports

Design Limitation Statement

The process skid is subject to the following limitations:

  • It is rated only for the design pressure and temperature specified on the datasheet; operation outside these limits voids the design
  • Field modification of piping or equipment after site installation requires re-rating and re-testing per original code
  • Skid must be installed on a level foundation of adequate bearing capacity (≥ 100 kN/m² typical); unlevel installation causes misalignment and seal/shaft failure in rotating equipment
  • Not suitable for processes requiring frequent layout changes – modifications to skid piping are constrained by existing frame and equipment placement
  • Not suitable for highly erosive service (solids content > 2% by weight) without erosion-resistant linings or reducers
  • Skid performance is verified only for the process conditions specified at FAT; changes in fluid composition or flow rate may affect pump/compressor curve and control tuning
Overall Rating
4.0
Based On Recent Reviews
Rating Snapshot
5
33%
4
33%
3
33%
2
0
1
0
All Reviews
R
R*l from India
Nov 5.2025
Very cost-competitive compared to European suppliers without compromising safety. The ASME certification was validated by our third-party inspector from Lloyd's Register. We used this reactor for our diesel hydrodesulfurization unit—startup was smooth, no hot spots or leakage issues. The vendor provided excellent Hindi-speaking technical support during commissioning. For Indian market, they even offered flexible payment terms. Highly recommended for developing economy projects.
T
Tanaka from Japan
Jul 26.2025
The QA/QC system is comparable to Japanese pressure vessel manufacturers. We requested additional UT testing on all Category A joints, and they accommodated without delay. The external surface preparation (Sa2.5 blasting + epoxy coating) was executed perfectly for our coastal installation. The 200,000L capacity with such a compact footprint demonstrates excellent engineering optimization. 納期も守られました。Will consider for future LNG pre-treatment projects.
M
Mitchell from United States
Jun 17.2025
We've been sourcing pressure vessels for 30 years, and this unit's ASME U-stamp certification gave us confidence from day one. The SA516 GR.70 material traceability documentation was impeccable—full MTRs, NDE reports, and third-party inspection by TÜV. Delivery to Houston was 3 weeks ahead of schedule. The 200kL capacity fits perfectly into our hydrocracker expansion project. Weld quality exceeded API 510 standards. Definitely adding this manufacturer to our approved vendor list.
Related Products
Send An Inquiry